The engine gives you dates; PC.o's analysis tells you what they mean. Here, how edits reach the reports, and how a baseline keeps the promise.
On an upload, Run analysis asks to Save as first. The upload stays; the copy is yours. Run analysis re-runs PC.o's analysis on the current dates. The schedule's reports are overwritten on their next run.
The flash says Analysis queued. It appears on the Files page when done: patience, then Files. The copy now has its own analysis. Its row menu offers Analysis, separate from the upload's.
Edit again and the pill says the analysis is behind: run on one revision, the schedule at another. On the Files page the word is Out of date; hover it and the tooltip names both revisions.
Schedule options, Analysis reruns, sets when it reruns: on demand, when the editing session ends, or never automatically. Tools, Compare Schedules: the upload is the Target, the copy the Update, as with any two schedules.
Activity Comparison Information counts one activity added. The rest of the dashboard has an entry of its own. Schedule, Baselines: another schedule, or this one, pinned at a revision. The copy starts with As uploaded.
Pick this schedule, call it Contract baseline, press Add: pin before you change. Nothing is copied. Both now sit in the list; the radio picks the active one, and None switches the strip off.
The strip under the bar keeps the baseline while the bar moves on. The chip names which. View, Columns: choose the Baseline preset.
The grid gains Baseline start and finish, the two variances, and Baseline TF: the schedule against the pin. Views, Bar styles: Baseline bars makes the strip follow the active baseline.
Export with a baseline, and PC.o asks whose planned dates go in the file: the baseline's, or this schedule's own.
That was analysis and baselines. Next in the Guide: scheduling that survives the site, from the article.
Taken from the video’s English captions.
THE SERIES Beta All 55 Scheduler videos, in order, 96 min 39 s end to end.
- 1The Scheduler in five minutesRunning time 2:50
- 2New to schedulingRunning time 4:14
- 3You know Microsoft ProjectRunning time 4:01
- 4New to scheduling on a P6 projectRunning time 4:16
- 5You know P6Running time 4:09
- 6Adding the Scheduler to a Basic accountRunning time 1:07
- 7Viewer or editor: which one you haveRunning time 1:41
- 8Open a scheduleRunning time 1:48
- 9New schedule and your defaultsRunning time 1:49
- 10Adding and deleting activitiesRunning time 0:56
- 11Indent, outdent and the WBSRunning time 0:44
- 12Durations and the sheetRunning time 1:19
- 13Drag a bar; undo and redoRunning time 0:50
- 14Milestones and activity typesRunning time 0:35
- 15The Details panelRunning time 0:47
- 16Editing activitiesRunning time 2:16
- 17Schedule options and settingsRunning time 2:16
- 18CalendarsRunning time 1:51
- 19Links: relationships, lags and leadsRunning time 2:01
- 20Constraints and datesRunning time 1:56
- 21Scenario 1 · a Microsoft Project file, Simple modeRunning time 1:58
- 22Scenario 2 · a Microsoft Project file, Full modeRunning time 2:29
- 23Scenario 3 · a P6 file, Simple modeRunning time 1:49
- 24Scenario 4 · a P6 file, Full modeRunning time 3:02
- 25How scheduling worksRunning time 1:48
- 26Switch engine: Standard and AdvancedRunning time 1:40
- 27Links: the four types, lag and leadRunning time 1:02
- 28Links by shorthandRunning time 0:47
- 29Links by nameRunning time 0:36
- 30Logic lines and off-screen partnersRunning time 0:33
- 31Columns, views, sort, filter and searchRunning time 2:13
- 32Columns and presetsRunning time 0:46
- 33Views, sort, filter and findRunning time 1:18
- 34The GanttRunning time 1:53
- 35Updating progress yourselfRunning time 1:54
- 36Resources, costs and the live cashflowRunning time 2:12
- 37Resources and assignmentsRunning time 1:01
- 38Costs and the live cashflowRunning time 1:19
- 39Curves and periodsRunning time 1:09
- 40Earned value against the baselineRunning time 1:20
- 41Usage and over-allocationRunning time 1:06
- 42Working with others: one editor at a timeRunning time 1:51
- 43Sharing and live linksRunning time 1:58
- 44Saving, Save as and recoveryRunning time 1:49
- 45Analysis copies and revertRunning time 1:13
- 46The update processRunning time 2:16
- 47Exports, print and Excel in and outRunning time 2:03
- 48Run analysis, compare and baselinesWatchingRunning time 2:20
- 49Exports and printRunning time 1:06
- 50Excel in and outRunning time 1:06
- 51Scheduling that survives the siteRunning time 1:47
- 52Logic, lags and leads: the practiceRunning time 1:50
- 53You were sent a schedule linkRunning time 1:18
- 54The viewer with a Basic planRunning time 1:28
- 55You were asked for an updateRunning time 1:13