Milestones and activity types

Add milestone below, the Type cell as a typed list (Task, Start milestone, Finish milestone, Level of effort), and Add many with a 0d milestone.

Running time 0:35CaptionedNo account needed to watchVideo 14 of 55

Build · 6 of 10. Each mark’s length is its running time.

TRANSCRIPTEvery word of the video, as text.

Read the transcript

Some activities take time; others merely happen. Here are milestones, the four types, and a quick way to add several.

Add milestone below: a point in time, no duration, a diamond on the chart. The Type cell is a typed list: Task, Start milestone, Finish milestone, or Level of effort.

Add many takes a list, one line each. A duration after the name; 0d makes a milestone.

That was types. Next in the Guide: the Details panel, where every field of an activity lives.