A schedule is activities and the links between them. Four kinds of link, a lag, a lead, and two habits that keep them honest.
Select an activity and open Predecessors: who it waits for, the kind of link, and the lag. Four kinds. Finish-to-start comes first: this starts when that finishes.
Start-to-start: Erect steel begins when Pour footings begins. Finish-to-finish: they end together. Start-to-finish is rare. The tick under Driving marks the link that sets the date. The other has room to spare.
A lag is a wait: two working days after the footings cure, the steel goes up. On a Standard schedule: working days, elapsed days, or a share of the predecessor's duration.
A negative lag is a lead: the next one starts before this one is done. Use it rarely. Add… is the Full way to make a link: search, pick, then choose the kind and the lag.
Type a link by name and lag: Erect steel plus two days. Spacing and case do not matter. View, Logic lines, draws or hides the links. On a big schedule it asks first; lines cost time.
A line to the edge means a partner is off screen. Go to successor lists them. Go to predecessor does the same, backwards: right-click, then choose from the list.
First habit: no open ends. Commission leads nowhere, so Handover does not wait for it. Second habit: a lead hides a risk. Here the steel starts three days early; split the work instead.
The lead is gone. If steel can really start early, split Erect steel and link the first half. Successors is the same story from the other side: one link, seen from both ends.
That was links. Next in the Guide: constraints, the dates you pin, and what each kind does to the engine.
Taken from the video’s English captions.
THE SERIES Beta All 55 Scheduler videos, in order, 96 min 39 s end to end.
- 1The Scheduler in five minutesRunning time 2:50
- 2New to schedulingRunning time 4:14
- 3You know Microsoft ProjectRunning time 4:01
- 4New to scheduling on a P6 projectRunning time 4:16
- 5You know P6Running time 4:09
- 6Adding the Scheduler to a Basic accountRunning time 1:07
- 7Viewer or editor: which one you haveRunning time 1:41
- 8Open a scheduleRunning time 1:48
- 9New schedule and your defaultsRunning time 1:49
- 10Adding and deleting activitiesRunning time 0:56
- 11Indent, outdent and the WBSRunning time 0:44
- 12Durations and the sheetRunning time 1:19
- 13Drag a bar; undo and redoRunning time 0:50
- 14Milestones and activity typesRunning time 0:35
- 15The Details panelRunning time 0:47
- 16Editing activitiesRunning time 2:16
- 17Schedule options and settingsRunning time 2:16
- 18CalendarsRunning time 1:51
- 19Links: relationships, lags and leadsWatchingRunning time 2:01
- 20Constraints and datesRunning time 1:56
- 21Scenario 1 · a Microsoft Project file, Simple modeRunning time 1:58
- 22Scenario 2 · a Microsoft Project file, Full modeRunning time 2:29
- 23Scenario 3 · a P6 file, Simple modeRunning time 1:49
- 24Scenario 4 · a P6 file, Full modeRunning time 3:02
- 25How scheduling worksRunning time 1:48
- 26Switch engine: Standard and AdvancedRunning time 1:40
- 27Links: the four types, lag and leadRunning time 1:02
- 28Links by shorthandRunning time 0:47
- 29Links by nameRunning time 0:36
- 30Logic lines and off-screen partnersRunning time 0:33
- 31Columns, views, sort, filter and searchRunning time 2:13
- 32Columns and presetsRunning time 0:46
- 33Views, sort, filter and findRunning time 1:18
- 34The GanttRunning time 1:53
- 35Updating progress yourselfRunning time 1:54
- 36Resources, costs and the live cashflowRunning time 2:12
- 37Resources and assignmentsRunning time 1:01
- 38Costs and the live cashflowRunning time 1:19
- 39Curves and periodsRunning time 1:09
- 40Earned value against the baselineRunning time 1:20
- 41Usage and over-allocationRunning time 1:06
- 42Working with others: one editor at a timeRunning time 1:51
- 43Sharing and live linksRunning time 1:58
- 44Saving, Save as and recoveryRunning time 1:49
- 45Analysis copies and revertRunning time 1:13
- 46The update processRunning time 2:16
- 47Exports, print and Excel in and outRunning time 2:03
- 48Run analysis, compare and baselinesRunning time 2:20
- 49Exports and printRunning time 1:06
- 50Excel in and outRunning time 1:06
- 51Scheduling that survives the siteRunning time 1:47
- 52Logic, lags and leads: the practiceRunning time 1:50
- 53You were sent a schedule linkRunning time 1:18
- 54The viewer with a Basic planRunning time 1:28
- 55You were asked for an updateRunning time 1:13