Sometimes a date is a fact: a delivery, a contract. Here is how to tell the engine, and how not to.
Calendar and constraints holds an activity's dates: a primary constraint, its date, and a secondary one. Nine kinds. Most are a floor or a ceiling on a start or a finish; two are mandates.
Start on or after: the steel waits for its delivery. Type the date as month, day, year. A secondary constraint closes the other side: a floor and a ceiling on one activity.
In the grid, the Constraint and Constraint date columns show it: day, month name, year. Press F9: the engine honours the floor. Fabricate steel moves, the finish follows, and Driver says why.
Handover: Finish on or before the contract date. A ceiling, so the finish does not move. Instead: negative float. The chain is five days late against the target, and Late finds it.
Under Project, Must finish by is one target for the whole schedule. Run past it, float goes negative. As late as possible slides Order fit-out to its late date: handy for orders and payments, little else.
Mandatory start overrides logic: the steel goes up before the footings are poured. The schedule lies. First, draw the logic. A delivery is a milestone and a link, not a constraint.
Second, few constraints, and targets rather than mandates. One ceiling on the handover is enough. A date can carry a time: type it after the date. Schedule options sets how it displays.
That was constraints. Next in the Guide: the four scenarios, starting with a Microsoft Project file in Simple mode.
Taken from the video’s English captions.
THE SERIES Beta All 55 Scheduler videos, in order, 96 min 39 s end to end.
- 1The Scheduler in five minutesRunning time 2:50
- 2New to schedulingRunning time 4:14
- 3You know Microsoft ProjectRunning time 4:01
- 4New to scheduling on a P6 projectRunning time 4:16
- 5You know P6Running time 4:09
- 6Adding the Scheduler to a Basic accountRunning time 1:07
- 7Viewer or editor: which one you haveRunning time 1:41
- 8Open a scheduleRunning time 1:48
- 9New schedule and your defaultsRunning time 1:49
- 10Adding and deleting activitiesRunning time 0:56
- 11Indent, outdent and the WBSRunning time 0:44
- 12Durations and the sheetRunning time 1:19
- 13Drag a bar; undo and redoRunning time 0:50
- 14Milestones and activity typesRunning time 0:35
- 15The Details panelRunning time 0:47
- 16Editing activitiesRunning time 2:16
- 17Schedule options and settingsRunning time 2:16
- 18CalendarsRunning time 1:51
- 19Links: relationships, lags and leadsRunning time 2:01
- 20Constraints and datesWatchingRunning time 1:56
- 21Scenario 1 · a Microsoft Project file, Simple modeRunning time 1:58
- 22Scenario 2 · a Microsoft Project file, Full modeRunning time 2:29
- 23Scenario 3 · a P6 file, Simple modeRunning time 1:49
- 24Scenario 4 · a P6 file, Full modeRunning time 3:02
- 25How scheduling worksRunning time 1:48
- 26Switch engine: Standard and AdvancedRunning time 1:40
- 27Links: the four types, lag and leadRunning time 1:02
- 28Links by shorthandRunning time 0:47
- 29Links by nameRunning time 0:36
- 30Logic lines and off-screen partnersRunning time 0:33
- 31Columns, views, sort, filter and searchRunning time 2:13
- 32Columns and presetsRunning time 0:46
- 33Views, sort, filter and findRunning time 1:18
- 34The GanttRunning time 1:53
- 35Updating progress yourselfRunning time 1:54
- 36Resources, costs and the live cashflowRunning time 2:12
- 37Resources and assignmentsRunning time 1:01
- 38Costs and the live cashflowRunning time 1:19
- 39Curves and periodsRunning time 1:09
- 40Earned value against the baselineRunning time 1:20
- 41Usage and over-allocationRunning time 1:06
- 42Working with others: one editor at a timeRunning time 1:51
- 43Sharing and live linksRunning time 1:58
- 44Saving, Save as and recoveryRunning time 1:49
- 45Analysis copies and revertRunning time 1:13
- 46The update processRunning time 2:16
- 47Exports, print and Excel in and outRunning time 2:03
- 48Run analysis, compare and baselinesRunning time 2:20
- 49Exports and printRunning time 1:06
- 50Excel in and outRunning time 1:06
- 51Scheduling that survives the siteRunning time 1:47
- 52Logic, lags and leads: the practiceRunning time 1:50
- 53You were sent a schedule linkRunning time 1:18
- 54The viewer with a Basic planRunning time 1:28
- 55You were asked for an updateRunning time 1:13