Links are easy to draw, and easy to draw wrong. Four habits from the best-practice article, each shown on a schedule with a fault.
First habit: no open ends. Backfill has no successor, so its thirteen days of float are never tested. Link it to Handover, and the same thirteen days become a real limit: Handover now waits for it.
Second habit: finish-to-start is the default, nine links in ten as a target. The others need a reason. By location, wall two waits for wall one's pour, and the formwork crew idles. Handover: 21 December.
Linking by crew: Wall 2 formwork waits for Wall 1 formwork, not for the pour. By crew, formwork moves wall to wall and rebar follows. Same link type, true sequence: Handover, 8 December.
Third habit: a lag that is really work is an activity. Curing is three days of something happening. Add it with Edit, Add many: one line, Cure 3d. It lands after the selected row.
Make it an activity: Cure, finish-to-start, lag zero. Now it can be seen, updated and reported. Fourth habit: no leads. Mobilise starts five days before procurement ends, with no float: a hidden risk.
Procurement slips two days, to seventeen, and Handover follows: 10 December. A lead promised time nobody had. Split it: order, then deliver; mobilise after the order. Ten days of float, and an honest 11 December.
The longest path runs Order, Deliver, then the formwork, wall to wall. Mobilise has room to spare.
That was the logic audit. Last in the Guide: the whole Scheduler in five minutes.
Taken from the video’s English captions.
THE SERIES Beta All 55 Scheduler videos, in order, 96 min 39 s end to end.
- 1The Scheduler in five minutesRunning time 2:50
- 2New to schedulingRunning time 4:14
- 3You know Microsoft ProjectRunning time 4:01
- 4New to scheduling on a P6 projectRunning time 4:16
- 5You know P6Running time 4:09
- 6Adding the Scheduler to a Basic accountRunning time 1:07
- 7Viewer or editor: which one you haveRunning time 1:41
- 8Open a scheduleRunning time 1:48
- 9New schedule and your defaultsRunning time 1:49
- 10Adding and deleting activitiesRunning time 0:56
- 11Indent, outdent and the WBSRunning time 0:44
- 12Durations and the sheetRunning time 1:19
- 13Drag a bar; undo and redoRunning time 0:50
- 14Milestones and activity typesRunning time 0:35
- 15The Details panelRunning time 0:47
- 16Editing activitiesRunning time 2:16
- 17Schedule options and settingsRunning time 2:16
- 18CalendarsRunning time 1:51
- 19Links: relationships, lags and leadsRunning time 2:01
- 20Constraints and datesRunning time 1:56
- 21Scenario 1 · a Microsoft Project file, Simple modeRunning time 1:58
- 22Scenario 2 · a Microsoft Project file, Full modeRunning time 2:29
- 23Scenario 3 · a P6 file, Simple modeRunning time 1:49
- 24Scenario 4 · a P6 file, Full modeRunning time 3:02
- 25How scheduling worksRunning time 1:48
- 26Switch engine: Standard and AdvancedRunning time 1:40
- 27Links: the four types, lag and leadRunning time 1:02
- 28Links by shorthandRunning time 0:47
- 29Links by nameRunning time 0:36
- 30Logic lines and off-screen partnersRunning time 0:33
- 31Columns, views, sort, filter and searchRunning time 2:13
- 32Columns and presetsRunning time 0:46
- 33Views, sort, filter and findRunning time 1:18
- 34The GanttRunning time 1:53
- 35Updating progress yourselfRunning time 1:54
- 36Resources, costs and the live cashflowRunning time 2:12
- 37Resources and assignmentsRunning time 1:01
- 38Costs and the live cashflowRunning time 1:19
- 39Curves and periodsRunning time 1:09
- 40Earned value against the baselineRunning time 1:20
- 41Usage and over-allocationRunning time 1:06
- 42Working with others: one editor at a timeRunning time 1:51
- 43Sharing and live linksRunning time 1:58
- 44Saving, Save as and recoveryRunning time 1:49
- 45Analysis copies and revertRunning time 1:13
- 46The update processRunning time 2:16
- 47Exports, print and Excel in and outRunning time 2:03
- 48Run analysis, compare and baselinesRunning time 2:20
- 49Exports and printRunning time 1:06
- 50Excel in and outRunning time 1:06
- 51Scheduling that survives the siteRunning time 1:47
- 52Logic, lags and leads: the practiceWatchingRunning time 1:50
- 53You were sent a schedule linkRunning time 1:18
- 54The viewer with a Basic planRunning time 1:28
- 55You were asked for an updateRunning time 1:13