Two engines, one schedule. Here is what switching changes, what it never changes, and how to go back.
The badge says which engine runs this schedule. Advanced behaves similarly to P6 in activity types and float. Schedule, Switch engine, Convert to Standard. Nothing happens yet: the engine runs a dry run first.
The dry run counts what would change, and promises what will not: no dates move, or it refuses. Converted. The same dates, a different rule book, and a Revert button for a few seconds.
What changed is vocabulary and options: a finish milestone is simply a milestone here. Vocabulary moves with the engine: Driver reads differently, and Longest path is an Advanced column.
Standard behaves similarly to Microsoft Project in its options: hours per day, split tasks, honoured constraints. File, Export, Conversion log: an Excel file of every element that changed. Keep it with the schedule.
On a Standard schedule XER and P6 XML are greyed: those files are written from the Advanced engine. Pressed anyway, it says so: convert to Advanced first, then export.
Unscheduled changes grey the switch: Schedule (F9) first. An upload asks to be saved as a PC.o Schedule. Revert puts everything back, element by element. Edit after converting and the revert is refused: it says so.
That was the switch. Next in the Guide: a schedule from nothing, typed as a list.
Taken from the video’s English captions.
THE SERIES Beta All 55 Scheduler videos, in order, 96 min 39 s end to end.
- 1The Scheduler in five minutesRunning time 2:50
- 2New to schedulingRunning time 4:14
- 3You know Microsoft ProjectRunning time 4:01
- 4New to scheduling on a P6 projectRunning time 4:16
- 5You know P6Running time 4:09
- 6Adding the Scheduler to a Basic accountRunning time 1:07
- 7Viewer or editor: which one you haveRunning time 1:41
- 8Open a scheduleRunning time 1:48
- 9New schedule and your defaultsRunning time 1:49
- 10Adding and deleting activitiesRunning time 0:56
- 11Indent, outdent and the WBSRunning time 0:44
- 12Durations and the sheetRunning time 1:19
- 13Drag a bar; undo and redoRunning time 0:50
- 14Milestones and activity typesRunning time 0:35
- 15The Details panelRunning time 0:47
- 16Editing activitiesRunning time 2:16
- 17Schedule options and settingsRunning time 2:16
- 18CalendarsRunning time 1:51
- 19Links: relationships, lags and leadsRunning time 2:01
- 20Constraints and datesRunning time 1:56
- 21Scenario 1 · a Microsoft Project file, Simple modeRunning time 1:58
- 22Scenario 2 · a Microsoft Project file, Full modeRunning time 2:29
- 23Scenario 3 · a P6 file, Simple modeRunning time 1:49
- 24Scenario 4 · a P6 file, Full modeRunning time 3:02
- 25How scheduling worksRunning time 1:48
- 26Switch engine: Standard and AdvancedWatchingRunning time 1:40
- 27Links: the four types, lag and leadRunning time 1:02
- 28Links by shorthandRunning time 0:47
- 29Links by nameRunning time 0:36
- 30Logic lines and off-screen partnersRunning time 0:33
- 31Columns, views, sort, filter and searchRunning time 2:13
- 32Columns and presetsRunning time 0:46
- 33Views, sort, filter and findRunning time 1:18
- 34The GanttRunning time 1:53
- 35Updating progress yourselfRunning time 1:54
- 36Resources, costs and the live cashflowRunning time 2:12
- 37Resources and assignmentsRunning time 1:01
- 38Costs and the live cashflowRunning time 1:19
- 39Curves and periodsRunning time 1:09
- 40Earned value against the baselineRunning time 1:20
- 41Usage and over-allocationRunning time 1:06
- 42Working with others: one editor at a timeRunning time 1:51
- 43Sharing and live linksRunning time 1:58
- 44Saving, Save as and recoveryRunning time 1:49
- 45Analysis copies and revertRunning time 1:13
- 46The update processRunning time 2:16
- 47Exports, print and Excel in and outRunning time 2:03
- 48Run analysis, compare and baselinesRunning time 2:20
- 49Exports and printRunning time 1:06
- 50Excel in and outRunning time 1:06
- 51Scheduling that survives the siteRunning time 1:47
- 52Logic, lags and leads: the practiceRunning time 1:50
- 53You were sent a schedule linkRunning time 1:18
- 54The viewer with a Basic planRunning time 1:28
- 55You were asked for an updateRunning time 1:13